The Federal Government has postponed the distribution of electricity meters under the ₦700 billion Presidential Metering Initiative (PMI) until 2027, two years after funds for the project were disbursed.
The initiative, approved in November 2023, was designed to address Nigeria's persistent electricity metering gap, eliminate unfair estimated billing, and improve revenue collection in the power sector.
According to a factsheet released by the Nigerian Electricity Regulatory Commission (NERC), the programme will commence distribution with 750,000 meters in 2027.
The delay comes despite earlier plans by the government to begin distributing 1.1 million meters by December 2025, followed by the deployment of two million meters annually over five years.
The PMI is also expected to complement the World Bank-funded Distribution Sector Recovery Programme (DISREP), which aims to deploy approximately 3.2 million smart meters across the electricity sector.
₦700bn Disbursed in Seven Tranches
Documents from the Federation Account Allocation Committee (FAAC) show that PMI-Smart Grid Development Limited received the funds in seven tranches between May and November 2024.
The first tranche of ₦120 billion was disbursed on May 13, 2024, followed by ₦100 billion on June 10 and another ₦100 billion on July 16.
An additional ₦100 billion was released on August 16, another ₦100 billion on September 16, and a further ₦100 billion on October 11.
The final tranche of ₦80 billion was disbursed on November 10, bringing the total funding to ₦700 billion.
Despite the disbursements, the government has yet to commence the planned nationwide distribution under the initiative.
Nigerians Spend ₦133.9bn on Electricity Meters
Data obtained by Daily Trust indicate that electricity distribution companies (DisCos) issued 1,645,004 meters under five existing schemes between 2025 and the second quarter of 2026.
The schemes include the Meter Asset Provider programme, the Distribution Sector Recovery Programme, the Meter Acquisition Fund, vendor financing, and DisCo-financed metering.
Of the total meters deployed, 892,859 were supplied through the Meter Asset Provider scheme, under which customers pay for meters and receive refunds through electricity tokens over an agreed period.
Using an estimated average price of ₦150,000 per meter, the report calculated that Nigerians spent approximately ₦133.93 billion purchasing meters through the scheme.
Meter prices vary depending on their specifications, with single-phase meters costing up to ₦120,000 and three-phase meters exceeding ₦200,000.
The delay in the presidential initiative has raised concerns about the financial burden on consumers, particularly low-income households struggling with estimated electricity bills.
Metering Gap Remains a Major Challenge
NERC's latest report cited in the publication indicates that Nigeria's metering deficit declined to 4,704,224 in August 2026, with approximately 8.05 million customers having meters.
However, energy-sector observers have questioned whether the figures accurately reflect the number of unmetered electricity consumers.
They argue that some buildings accommodating dozens of households are classified by DisCos as single customers, potentially understating the actual metering gap.
The absence of prepaid meters has also continued to fuel complaints about excessive billing, with consumers frequently disputing charges they believe do not reflect their actual electricity consumption.
Band A Customers Receive Priority
An official of the Abuja Electricity Distribution Company (AEDC), who spoke anonymously, said Band A customers were being prioritised because of their importance to the financial stability of the electricity market.
The official added that some long-standing customers were also receiving meters where their electricity consumption was considered inconsistent with the power supplied to them.
However, some applicants have waited months without receiving meters.
An Abuja resident, Ibrahim Idris, said he applied for a meter in January but had yet to receive one, despite waiting for 10 months.
He complained that the distribution company had neither provided an update on his application nor offered an alternative.
Idris said he had installed a solar power system at home, reducing his dependence on the electricity grid and his urgency to obtain a meter.
Another customer, Mohammed Saheed, said he was asked to pay ₦120,000 to obtain a meter, while Isaac Emmanuel alleged that he paid an installer ₦30,000 to install a meter he had purchased.
These complaints have intensified concerns about possible unofficial charges and delays in the metering process.
Consumer Group Calls for Accountability
The President of the Nigeria Consumer Protection Network, Kunle Kola Olubiyo, said the ₦700 billion initiative could significantly improve accountability in the electricity sector.
He explained that the funding, sourced through FAAC, was expected to support a fair distribution of meters across states, with priority given to vulnerable consumers.
Olubiyo said the initiative was designed to reduce the metering gap, end unfair estimated billing, and strengthen the financial stability of the power sector.
He also questioned whether the government had met its December 2025 deadline for the initial deployment of 1.1 million meters.
Olubiyo called for greater transparency regarding the implementation of both the presidential initiative and the World Bank-supported metering programme.
Energy expert Lanre Elatuyi warned that consumers and electricity distribution companies would continue to face difficulties as long as large numbers of customers remained unmetered.
According to him, underbilling prevents DisCos from recovering the cost of electricity supplied, while overbilling often leads to disputes and resistance from customers.
He stressed that the inability of some consumers to pay for meters upfront remains a major challenge for an electricity sector already facing financial difficulties.
Elatuyi urged the Federal Government to provide the public with a clear update on the status of the presidential initiative.
Government Yet to Explain the Delay
The Ministry of Power did not provide an explanation for the postponement when contacted by Daily Trust.
The ministry's spokesperson, Clement Ezeora, said he was new to the position and did not have information about the project.
The minister's media aide, Adeola Adelabu, directed enquiries to the Office of the Special Adviser on Energy, where the initiative is domiciled.
However, calls and messages to the project's Director and Chief Executive Officer, Obafemi Solebo, and three other PMI officials reportedly went unanswered.
The initiative also includes plans to train more than 5,000 Nigerians in meter installation and strengthen local meter manufacturers in line with the government's local-content policy.
The training programme, organised by the National Power Training Institute of Nigeria (NAPTIN), began in July 2026, with participants undergoing training in batches. The Nigerian Electricity Management Services Agency (NEMSA) is responsible for certification and compliance standards.
Despite progress on the training component, the delay in meter distribution has left consumers waiting for relief from estimated billing.
With the first phase now scheduled to begin in 2027 with 750,000 meters, questions remain over the reasons for the delay, the use of the funds already disbursed, and whether the government can meet its revised implementation timeline.